100 TOP Construction Planning and Management Multiple choice Questions and Answers pdf

91.    The most suitable type of equipment for compaction of cohesive soils is
a)    Smooth-wheeled rollers
b)    Vibratory rollers
c)    Sheep foot rollers
d)    Tampers
Ans: c

92.    For excavating utility trenches with precise control of depth, the excavation equipment used is
a)    Hoe
b)    Shovel
c)    Drag line
d)    None of the above
Ans: a

93.    The basic action involved in sheep foot rolling is
a)    Kneading
b)    Pressing
c)    Tamping
d)    Vibration
Ans: a

94.    Batching refers to
a)    controlling the total quantity at each batch
b)    weighing accurately, the quantity of each material for a job before mixing
c)    controlling the quantity of each material into each batch
d)    adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch
Ans: c

95.    Consider the following statements:
Wheeled tractors are replacing crawler tractors because
1.    wheeled tractors travel faster.
2.    crawler tractors are more expensive.
3.    track parts of a crawler wear out quickly.
4.    crawler tractors have stick control.
Of these statements
a)    1,3 and 4 are correct
b)    2, 3 and 4 are correct
c)    1,2 and 3 are correct
d)    1, 2 and 4 are correct
Ans: c

96. The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted, and pneumatic tyre-mounted machines would be respectively
a)    80 and 90
b)    90 and 80
c)    85 and 75
d)    75 and 83
Ans: d

97.    Sensitivity analysis is a study of
a)    comparison of profit and loss
b)    comparison of assets and liabilities
c)    change in output due to change in input
d)    economics of cost and benefits of the project
Ans: c

98.    In the time-cost optimization, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having
a)    longest duration
b)    highest cost slope
c)    least cost slope
d)    shortest duration
Ans: c

99.    Preliminary project report for a road project must contain
a)    the detailed estimated cost based on detailed design
b)    the several alternatives of the project that have been considered
c)    the soil survey, traffic survey, concept design and approximate cost
d)    the contract documents for inviting tenders
Ans: c