Construction Planning and Management Multiple Choice Questions and Answers for freshers and experienced pdf download free

1. PERT technique of network analysis is mainly useful for
a) small projects
b) large and complex projects
c)  research and development projects
d)  deterministic activities
Ans: c
 
2. Select the correct statement.
a)   Activity arrows in a CPM network are drawn to scale
b)   The tail of an arrow represents the finish of an activity
c)   Arrow bead represents the start of an activity
d)   none of the above
Ans: d

3. Which of the following is a weakness of bar chart ?
a)    interdependencies of activities
b)    project progress
c)    uncertainties
d)    all of the above
Ans: d

4. In the network shown in Fig. , activity 4-5 can be started only when

 
a)    activity 3-4 is completed
b)    activity 2—4 is completed
c)    activity 2-3 is completed
d)      activity 2-4 and 2>-A both are com-pleted
Ans: d

5. Which of the following is not a PERT event ?
a)    site investigation started
b)    sessional work completed
c)    bus starts from Jaipur
d)    class is being attended
Ans: d

6. In PERT analysis, the time estimates of activities  and  probability   of their  occurrence follow
a)    normal distribution curve
b)    Poisson's distribution curve
c)    Beta - distribution curve
d)    none of the above
Ans: c

7. The area under the Beta - distribution curve is divided into two equal parts by
a)    most likely time
b)    optimistic time
c)    pessimistic time
d)    expected time
Ans: d

8. According to Fulkerson's rule, what are the correct event numbers corresponding to events A, B, C, D,E, F and G of the network shown in Fig. ?
   
a)    1, 2,3, 4, 5, 6 and 7 respectively
b)    1, 3,2,4, 5,6 and 7 respectively
c)    1,2, 3, 5, 6,4 and 7 respectively
d)    1, 3,2, 5, 6,4 and 7 respectively
Ans: b

9.   With reference to the network shown in Fig. , which statement is incorrect ?

a)    Events 3 and 4 occur after event 2.
b)    Event 7 can occur after event 4.
c)    Event 7 precedes event 6.
d)    Event 5 follows event 3.
Ans: b

10.    In the network shown in Fig., the concurrent and preceding activities corresponding to activity 2-4 are respectively

a)    1-2 and 4-7
b)    2-3 and 1-2
c)    2-3 and 4-7
d)    1-2 and 3-6
Ans: b